WIBA#1 Construction Schedule 9/26/24 – 3/23/25

By September 26, 2024All Posts
The schedule for Pilon Construction Company for Water Improvement Benefit Area No. 1 is now available!
More information about WIBA#1:
  • 09/26-09/27: Mobilize equipment, material deliveries, layout, and put fittings together.
  • 09/30-10/18: Complete grubbing and begin excavation for watermain install on Drake Road, including rough grading.
  • 10/18-10/20: Mobilize equipment to Lawton Road and begin grubbing.
  • 10/21-11/08: Continue grubbing and start excavation for watermain install on Lawton Road.
  • 11/11-11/29: Mobilize equipment, perform grubbing, and install watermain on Ireland Road, continuing to the connection on Clarkson/Parma Townline Road.
  • 12/02-12/20: Mobilize, perform grubbing, and install watermain on Sweden Walker Road.
  • 01/06-01/17: Mobilize, perform grubbing, and install watermain on Redman Road (north end).
  • 01/20-02/07: Mobilize, perform grubbing, and install watermain on Countyline Road.
  • 02/10-02/14: Mobilize, perform grubbing, and install watermain on Redman Road (south end).
  • 02/17-03/14: Grubbing and watermain installation on Route 31 and Old Route 31.
  • 09/26-03/23: Service installation, filling, flushing, pressure testing, and sanitizing of the watermain will run concurrently as the mainline is being installed, subject to weather conditions and project encounters.